The Al Maktoum airport expansion is on schedule: in June 2026 the Dubai Government said phase one of Al Maktoum International will start operations in 2032, with contracts worth AED 13 billion under execution and more than AED 55 billion of new packages being prepared for award. For Dubai South, the district around the airport, that is a state-backed demand driver. The catch is timing: most of the homes being built there will be finished years before the airport opens.
Al Maktoum airport expansion: what was confirmed
- Opening: phase one on approved timelines, with operations from 2032.
- Money committed: packages above AED 13 billion under execution, including more than 17,000 concrete piles, and the second runway completed ahead of work on the existing one.
- Next contracts: more than AED 55 billion, including terminal substructure and superstructure, concourses, the people mover and baggage handling.
- Final scale: capacity of more than 260 million passengers and 12 million tonnes of cargo a year, five parallel runways and more than 430 aircraft stands, once the final phase is complete.
The government also plans a managed transfer of operations from Dubai International to the new airport. That is the long-run reason Dubai South matters: the city's main airport is moving to its doorstep.
Dubai South property today
Dubai South is already one of the busiest markets in the city. In the twelve months from November 2025 to October 2026, DLD data recorded:
| Dubai South, all property types | Figure |
|---|---|
| Sales | 16,431 (up 72% on the previous year) |
| Median sale price | AED 1.03m |
| Median price per sq ft | AED 1,640 (up 4%) |
| Gross yield | 8% |
| Median new-lease rent (yearly) | AED 72,000 |
| Median renewal rent (yearly) | AED 71,400 (up 15%) |
Gross yield as measured by DXB Interact on units both sold and rented in the period.
Over the past year it ranked first of 165 areas in Dubai by sales volume. The median price fell 35%, but that is a mix effect: many more smaller off-plan units sold. Price per sq ft, the cleaner measure, rose 4%.
Off plan property in Dubai South: the supply gap
This is the part brochures leave out. The DLD data shows 48 projects with 44,320 units in Dubai South's upcoming supply. By scheduled completion year:
| Year | Units planned to complete in Dubai South |
|---|---|
| 2027 | 11,616 |
| 2028 | 6,798 |
| 2029 | 6,852 |
| 2030 | 1,652 |
In 2027, Dubai South has more planned completions than any other area in the city. Developers launched 15,863 units there in 2024 and 12,698 in 2025. Most of those homes will be ready around three to five years before the airport's first phase opens.
The airport opens in 2032. Your tenants have to come from somewhere before then.
Until 2032, demand rests on what already exists: the logistics and aviation businesses around Dubai World Central, Expo City, and households priced out of more central areas. Rents have been firm, with renewals up 15%, but a wave of completions in 2027 will test them.
Al Maktoum airport, when will it open, and who should buy now
Dubai South suits patient capital: a buyer who can hold through the completion wave, accept softer rents for a period, and is buying for the decade the airport changes the district, not for a quick resale at handover.
It suits less well a buyer who needs rent to cover a mortgage from day one, or who plans to sell at completion alongside thousands of other new owners.
What I check on a Dubai South purchase
- Handover year against the supply table above. A 2027 completion competes with more than 11,000 units.
- Developer record and escrow. The basics in five checks before any off-plan purchase.
- Guarantees. In an area with this much supply, a rental guarantee is often how a developer moves units. Read why guarantees are priced in before you rely on one.
- Your exit. Who buys from you in 2030, and against how many identical units?
Frequently asked questions
When will Al Maktoum airport open?
The Dubai Government said in June 2026 that phase one will start operations in 2032, in line with approved timelines.
How big will Al Maktoum International be?
At full build-out, more than 260 million passengers a year, five parallel runways and more than 430 aircraft stands.
Is Dubai South property a good investment?
It can be, for a buyer with time. The airport is a real long-term driver, but more than 25,000 units are scheduled to complete in Dubai South between 2027 and 2030, so short-term rents and resale prices face competition.
If Dubai South is on your list, book a 30-minute call and bring the payment plan.
Sources: Dubai Media Office, 15 June 2026; Dubai Land Department transaction data via DXB Interact (Dubai South sales and rents, 1 November 2025 to 31 October 2026; area report and supply pipeline, retrieved 21 November 2026). Retrieved November 2026.